Schedule


Work Hours & Truck Route
Work Hours will be Monday through Friday
7:00 am to 6:00 pm
There will be no weekend work without special approval

Dump trucks will stage on site - No on street staging permitted

Work Flow
In general, progress will proceed along a work flow that includes:
Site Excavation:
- Grading and rocking site access and haul road
- Excavation of reservoir site
- Removal of excavated materials
- Stabilization and shoring of excavation site
Reservoir Construction:
- Boring and setting concrete footing pilings
- Construction retaining wall
- Install underlayment fabric
- Installing inlet and outlet piping
- Leveling engineered fill
- Forming, tying retaining bar, and pouring floor
- Forming, tying retaining bar, and pouring walls, support columns, and roof
- Install vents and hatches
- Apply cable wrapping
- Install pumping and mechanical components
Backfill
- Backfill and rough grade at reservoir
Final Grading and Sitework
- Final grading and site preparation of entire two reservoir site
- Installation of final fencing
- Coating new Reservoir 11 and re-coating existing Reservoir 6
- Installation of irrigation system
- Landscaping work

Site Section
Site section drawing showing post construction ground levels and backfill plan.